The earned value technique is a commonly used method of performance measurement.It integr

The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned

发布时间:2024-05-07
参考答案

正确答案:C
挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

相关问题
  • ● Routing protocols use different techniques for ass

    ● Routing protocols use different techniques for assigning(71)to individual networks.Further, each routing protocol forms a

    答案解析
  • ●(75) involves using mathematical techniques to forec

    ●(75) involves using mathematical techniques to forecast future outcomes based on historical results (75)A Trend analysisB Quality auditC Defect repair reviewD Flowcharting

    答案解析
  • (73) is one of the techniques used for estimating activity durations. (73)A.Analogous Es

    (73) is one of the techniques used for estimating activity durations (73)A.Analogous EstimatingB.Precedence Diagramming Method (PDM)C.Dependency DeterminationD.Schedule network Templates

    答案解析
  • Many useful tools and techniques are used in developing schedule. (72) is a schedule net

    Many useful tools and techniques are used in developing schedule. (72) is a schedule network analysis technique that modifie

    答案解析
  • ??Many useful tools and techniques are used in developing schedule.( 73)is a schedulenetwo

    ??Many useful tools and techniques are used in developing schedule ( 73) is a schedulenetwork analysis technique that modifie

    答案解析
  • involves using mathematical techniques to forecast future outcomes based on historical

    involves using mathematical techniques to forecast future outcomes based on historical results A.Trend analysisB.Quality auditC.Defect repair reviewD.Flowcharting

    答案解析
  • Many useful tools techniques are used in developing schedule. ( )s a schedule network anal

    Many useful tools techniques are used in developing schedule ( )s a schedule network analysis technique that modifies the

    答案解析
  • All the following tools and techniques are helpful to accurately confirming customers’ne

    All the following tools and techniques are helpful to accurately confirming customers’needs,except( 72 )。A questionnairesB prototyping approachesC fishbone diagramsD interviews

    答案解析
  • ______is one of the techniques used for estimating activity durations.A.Analogous Estimati

    ______is one of the techniques used for estimating activity durations.A.Analogous EstimatingB.Precedence Diagramming Method(PDM)C.Dependency DeterminationD.Schedule network Templates

    答案解析
  • ( )is a project management technique for measuring project performance progress.It has the

    ( )is a project management technique for measuring project performance progress It has the ability to combine measurements o

    答案解析

最新问题

Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5