They also helped build the vast network of railroads that ____ important trade centers essential to industrial grented.
A. had linked
B. link
C. Linking
D. linked
答案:D解析:首先可判断出此句是关系代词that 引导的定语从句。先行词是network ofrailroads,从句中缺少谓语动词,故可排除C。根据主句的时态,应用一般过去时,故选D。
The actual configuration of a PERT/CPM network _____
The actual configuration of a PERT CPM network _____ the amount of resources that can be devoted to the project A Increases B
答案解析The critical path in a schedule network is the path that:A.Takes the longest time to compl
The critical path in a schedule network is the path that:A Takes the longest time to completeB Must be done before any othe
答案解析Assume that you have a network where an activity on the critical path can be crashed by tw
Assume that you have a network where an activity on the critical path can be crashed by two weeks If the activity is ac
答案解析Once the logic of a network is laid out the project manager will conduct a forward pass a
Once the logic of a network is laid out, the project manager will conduct a forward pass and backward pass through the ne
答案解析The critical path in a network is the path that:A.Has the greatest degree of risk.B.Will e
The critical path in a network is the path that:A Has the greatest degree of risk B Will elongate the project if the activi
答案解析Which of the following networking methods allows us to show that the last % of one element
Which of the following networking methods allows us to show that the last % of one element cannot be completed until % of a previous element has been completed?A PERTB ADMC PDMD All of the above E A and C only
答案解析The basic terminology for networks includes:A.Activities events manpower skill levels a
The basic terminology for networks includes:A Activities, events, manpower, skill levels and slack B Activities, documentation, ev
答案解析The utility of network-based schedules:A.Reveals inter
The utility of network-based schedules:A Reveals interdependencies B Facilitates "what if" exercises C Highlights critical activities
答案解析An informal communication network on a project and within an organization is called a(n):A
An informal communication network on a project and within an organization is called a(n):A free upward flowB free horizontal flowC unrestricted communication flowD grapevineE open network
答案解析107The utility of network-based schedules: A.Reveals
107 The utility of network-based schedules:A Reveals interdependencies B Facilitates "what if" exercises C Highlights critical