199 Using the figure in the Special window, Activity "L" has an early start time of _____ weeks and an early finish time of _____ weeks.
A. 11, 13
B. 12, 14
C. 13, 15
D. 14, 16
E. 15, 17
发布时间:2024-04-25正确答案:E
Using the WBS shown in the Special window a typical work package would be:ASoftware devel
Using the WBS shown in the Special window, a typical work package would be:ASoftware developmentBSystems designCCodingDA, B, and CENone of the above
答案解析Using the table in the Special window Which task is completed?A.dig holeB.remove debrisC.
Using the table in the Special window, Which task is completed?A dig holeB remove debrisC surveyD set formsE place concrete
答案解析Using the WBS in the Special window an instance of a work package is:A.Build houseB.Excav
Using the WBS in the Special window, an instance of a work package is:A Build houseB ExcavateC Prepare FoundationD B and CE None of the above
答案解析Using the situation stated in the Special window what is the schedule variance for Case #
Using the situation stated in the Special window, what is the schedule variance for Case 8?A 1000B 2000C -1000D -2000E 0
答案解析Using the situation stated in the Special window what is present value of $1000 at 12% at
Using the situation stated in the Special window, what is present value of $1000 at 12% at the end of 5 years?A ¥3,605 00B ¥0 57C ¥567 00D ¥892 86E ¥3 61
答案解析Using the situation stated in the Special window what is net present value of an annual i
Using the situation stated in the Special window, what is net present value of an annual income flow of $1600 at 14% over the next three years?A ¥3,713 60B ¥0 68C ¥1,080 00D ¥476 19E ¥2 32
答案解析Using the situation stated in the Special window w
Using the situation stated in the Special window, what is the labor rate cost variance?A ¥5,500 00B ¥1,500 00C ¥-100 00D ¥-0 10E ¥5,600 00
答案解析Using the situation stated in the Special window what is the total price variance for dir
Using the situation stated in the Special window, what is the total price variance for direct material?A ¥140 00B ¥736 00C ¥0 02D ¥-350 00E ¥5,850 00
答案解析Using the situation stated in the Special window what is the total variable costs for pro
Using the situation stated in the Special window, what is the total variable costs for producing one widget?A ¥1,020B ¥1,010C ¥1,015D ¥20E None of the above
答案解析Using the problem stated in the Special window Calculate the deviation of duration for th
Using the problem stated in the Special window, Calculate the deviation of duration for the task, using the PERT concept of standard deviation of task duration A 0 5B 1C 1 8D 2 2E 2 8
答案解析Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5