● The work breakdown structure (WBS) is first developed in which scope management process?
A Initiation
B Scope planning
C Scope change control
D Scope Definition
E Scope verification
发布时间:2024-04-25正确答案:D
The work breakdown structure (WBS) is first developed in which scope management process?A.
The work breakdown structure (WBS) is first developed in which scope management process?A InitiationB Scope planningC Scope change controlD Scope DefinitionE Scope verification
答案解析A Work Berakdown Structure is most useful for:A.Identifying individual tasks for a project
A Work Berakdown Structure is most useful for:A Identifying individual tasks for a project B Scheduling the start of tasks C Developing a cost estimate D Determining potential delays E A and C
答案解析A work breakdown structure:A.assures all work is identified.B.subdivides the project into
A work breakdown structure:A assures all work is identified B subdivides the project into manageable segments C provides the project sponsor with a time-phase task summary D both A and B E All of the above
答案解析A work breakdown structure is most useful for:A.identifying individual tasks for a project
A work breakdown structure is most useful for:A identifying individual tasks for a projectB scheduling the start of tasksC developing a cost estimateD determining potential delaysE A and C
答案解析The work breakdown structure the work packages an
The work breakdown structure, the work packages, and the company"s accounting system are tied together through the:A Code
答案解析131The work breakdown structure the work packages
131 The work breakdown structure, the work packages, and the company"s accounting system are tied together through the:A Cod
答案解析146The work breakdown structure (WBS) is an excellent tool for objective control and evalu
146 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation Which of the following is
答案解析120The Work Breakdown Structure (WBS) is the basis for communicating: A.Project scope cos
120 The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Proj
答案解析154A Work Breakdown Structure: A.assures all work is identified B.subdivides the project i
154 A Work Breakdown Structure:A assures all work is identifiedB subdivides the project into manageable segmentsC provides the project sponsor with a time-phase task summaryD both A and BE All of the above
答案解析25A work breakdown structure is most useful for: A.identifying individual tasks for a proj
25 A work breakdown structure is most useful for:A identifying individual tasks for a projectB scheduling the start of tasksC developing a cost estimateD determining potential delaysE A and C