当前位置: 首页 > 职业资格 > 问题详情
问题

●The work breakdown structure (WBS) is first developed in which scope management process?A

● The work breakdown structure (WBS) is first developed in which scope management process?

A Initiation

B Scope planning

C Scope change control

D Scope Definition

E Scope verification

发布时间:2024-04-25
参考答案

正确答案:D

相关问题
  • The work breakdown structure (WBS) is first developed in which scope management process?A.

    The work breakdown structure (WBS) is first developed in which scope management process?A InitiationB Scope planningC Scope change controlD Scope DefinitionE Scope verification

    答案解析
  • A Work Berakdown Structure is most useful for:A.Identifying individual tasks for a project

    A Work Berakdown Structure is most useful for:A Identifying individual tasks for a project B Scheduling the start of tasks C Developing a cost estimate D Determining potential delays E A and C

    答案解析
  • A work breakdown structure:A.assures all work is identified.B.subdivides the project into

    A work breakdown structure:A assures all work is identified B subdivides the project into manageable segments C provides the project sponsor with a time-phase task summary D both A and B E All of the above

    答案解析
  • A work breakdown structure is most useful for:A.identifying individual tasks for a project

    A work breakdown structure is most useful for:A identifying individual tasks for a projectB scheduling the start of tasksC developing a cost estimateD determining potential delaysE A and C

    答案解析
  • The work breakdown structure the work packages an

    The work breakdown structure, the work packages, and the company"s accounting system are tied together through the:A Code

    答案解析
  • 131The work breakdown structure the work packages

    131 The work breakdown structure, the work packages, and the company"s accounting system are tied together through the:A Cod

    答案解析
  • 146The work breakdown structure (WBS) is an excellent tool for objective control and evalu

    146 The work breakdown structure (WBS) is an excellent tool for objective control and evaluation Which of the following is

    答案解析
  • 120The Work Breakdown Structure (WBS) is the basis for communicating: A.Project scope cos

    120 The Work Breakdown Structure (WBS) is the basis for communicating:A Project scope, cost control, schedule, qualityB Proj

    答案解析
  • 154A Work Breakdown Structure: A.assures all work is identified B.subdivides the project i

    154 A Work Breakdown Structure:A assures all work is identifiedB subdivides the project into manageable segmentsC provides the project sponsor with a time-phase task summaryD both A and BE All of the above

    答案解析
  • 25A work breakdown structure is most useful for: A.identifying individual tasks for a proj

    25 A work breakdown structure is most useful for:A identifying individual tasks for a projectB scheduling the start of tasksC developing a cost estimateD determining potential delaysE A and C

    答案解析

最新问题

Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5