当前位置: 首页 > 职业资格 > 问题详情
问题

92The project charter is developed by: A.senior management B.the customer C.the project ma

92 The project charter is developed by:

A. senior management

B. the customer

C. the project manager

D. both A and C

E. None of the above

发布时间:2024-04-25
参考答案

正确答案:D

相关问题
  • The scope baseline/project charter is prepared by th

    The scope baseline project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, projec

    答案解析
  • The project charter is developed by:A.senior managementB.the customerC.the project manager

    The project charter is developed by:A senior managementB the customerC the project managerD both A and CE None of the above

    答案解析
  • The project charter:A.Expresses upper management commitment to the project.B.Provides that

    The project charter:A Expresses upper management commitment to the project B Provides that authority by which the project will

    答案解析
  • The project scope/charter baseline includes:A.Summary

    The project scope charter baseline includes:A Summary of background conditions defining the project B Organization, authority and

    答案解析
  • 159The project scope/charter baseline includes: A.Summ

    159 The project scope charter baseline includes:A Summary of background conditions defining the project B Organization, authori

    答案解析
  • 35The project charter: A.Expresses upper management commitment to the project. B.Provides

    35 The project charter:A Expresses upper management commitment to the project B Provides that authority by which the project

    答案解析
  • 10The project charter is developed by: A.senior management Bthe customer C.the project man

    10 The project charter is developed by:A senior managementB the customerC the project managerD both A and CE None of the above

    答案解析
  • 123The scope baseline/project charter is prepared by

    123 The scope baseline project charter is prepared by the:A Project managerB Project manager and project officeC Project ma

    答案解析
  • ●The project scope/charter baseline includes:ASummary

    ● The project scope charter baseline includes:A Summary of background conditions defining the project B Organization, authority

    答案解析
  • ●The project charter:AExpresses upper management commi

    ● The project charter:A Expresses upper management commitment to the project B Provides that authority by which the project

    答案解析

最新问题