106The "control points" in the work breakdown structure used for isolated assignments to w

106 The "control points" in the work breakdown structure used for isolated assignments to work centers are referred to as:

A. Work packages.

B. Subtasks.

C. Tasks.

D. Code of accounts.

E. Integration points

发布时间:2024-04-25
参考答案

正确答案:C

相关问题
  • 188The "control points" in the work breakdown structu

    188 The "control points " in the work breakdown structure used for isolated assignments to work centers are referred to as:A Work packages B Subtasks C Tasks D Code of accounts E Integration points

    答案解析
  • Which of the following points is not included in the passage?___________

    Which of the following points is not included in the passage?___________A Industrial development includes the simplification of

    答案解析
  • Which of the following are included as part of a scope statement?A.Project justificationB.

    Which of the following are included as part of a scope statement?A Project justificationB Project deliverablesC Project objectivesD All of the aboveE B and C

    答案解析
  • Which of the following is not a scope management process?A.InitiationB.Scope planningC.Sco

    Which of the following is not a scope management process?A InitiationB Scope planningC Scope DefinitionD Scope change controlE Scope verification

    答案解析
  • In which of the following scope management processes is the scope management plan prepared

    In which of the following scope management processes is the scope management plan prepared?A InitiationB Scope planningC Scope DefinitionD Scope change controlE Scope verification

    答案解析
  • The project charter is prepared in which scope management process?A.InitiationB.Scope plan

    The project charter is prepared in which scope management process?A InitiationB Scope planningC Scope DefinitionD Scope change controlE Scope verification

    答案解析
  • In which of the following scope management processes are subject matter experts used?A.Ini

    In which of the following scope management processes are subject matter experts used?A InitiationB Scope planningC Scope DefinitionD Scope change controlE Scope verification

    答案解析
  • Which of the following are included in the Acquisition phase(s) of the project life cycle.

    Which of the following are included in the Acquisition phase(s) of the project life cycle A concept and developmentB de

    答案解析
  • Project alternatives are examined during the _____ phase of the projectA.conceptualB.finis

    Project alternatives are examined during the _____ phase of the projectA conceptualB finishC developmentD implementationE A and C

    答案解析
  • Mary: What are you working on? Susan: I'm doing

    Mary: What are you working on? Susan: I"m doing some embroidery Mary: ______ Susan: I don"t do very much, just for very

    答案解析

最新问题

Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5