102The major disadvantage of a bar chart is: A.Lack of time-phasing. B.Cannot be related t

102 The major disadvantage of a bar chart is:

A. Lack of time-phasing.

B. Cannot be related to calendar dates.

C. does not show activity interrelationships.

D. Cannot be related to manpower planning.

E. Cannot be related to cost estimates

发布时间:2024-04-25
参考答案

正确答案:C

相关问题
  • In which of the following scope management processes is the scope management plan prepared

    In which of the following scope management processes is the scope management plan prepared?A InitiationB Scope planningC Scope DefinitionD Scope change controlE Scope verification

    答案解析
  • Science is still ______ of the causes of many kinds of cancer.A.ignorantB.unconsciousC.con

    Science is still ______ of the causes of many kinds of cancer A.ignorantB.unconsciousC.consciousD.informed

    答案解析
  • ( ) is the use of computing ...deliverd as a service over a network.

    ( ) is the use of computing deliverd as a service over a network A Virtualzation B Internet of thingsC ClouD computer D ClouD computing

    答案解析
  • Don' t be afraid of asking for help_________it is needed. A. unless B. sinceC.

    Don " t be afraid of asking for help_________it is needed A. unlessB. sinceC. althoughD. when

    答案解析
  • The main idea of this passage is__________A. that vicious and dangerous sports sh

    The main idea of this passage is__________A. that vicious and dangerous sports should be banned by lawB. that people are

    答案解析
  • What is the purpose of the author in writing this passage?A. Legs become weaker~B

    What is the purpose of the author in writing this passage?A. Legs become weaker~B. Modern means of transportation make the

    答案解析
  • The attitude of the author toward advertisers isA. appreciativeB. trustworthyC. c

    The attitude of the author toward advertisers isA. appreciativeB. trustworthyC. criticalD. dissatisfactory

    答案解析
  • Project trade-offs vary betweenA.risk cost and sche

    Project trade-offs vary betweenA risk, cost and schedule B direct cost, indirect cost, and resource availabilityC quality, schedule and timeD cost, quality and scheduleE contract terms, scope and budget

    答案解析
  • During the planning phase of a project you realize that more than one functional departme

    During the planning phase of a project, you realize that more than one functional department possesses the skill and technic

    答案解析
  • The most common definition of project success is:A.Within timeB.Within time and costC.With

    The most common definition of project success is:A Within timeB Within time and costC Within time, cost and technical performan

    答案解析

最新问题

Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5