The primary source document for establishing the content of the Project Status Report is:A

The primary source document for establishing the content of the Project Status Report is:

A The project charter

B The Project Plan

C The ASTM Project Document Guide

D The summary work breakdown structure

发布时间:2024-04-25
参考答案

正确答案:B

相关问题
  • The project charter is a document designed to tell _____ exactly what the project entails.

    The project charter is a document designed to tell _____ exactly what the project entails AThe project managerBThe project officeCThe project teamDThe project sponsorEAnyone associated with the project

    答案解析
  • The process of choosing/documenting the best approach

    The process of choosing documenting the best approach to achieve the project objectives is part of:A The scope baseline B Scope authorizationC Scope definitionD Scope planning E All of the above

    答案解析
  • A legally binding document offered unilaterally is a _____ .Apurchase orderBscope of work

    A legally binding document offered unilaterally is a _____ A purchase orderB scope of work descriptionC contract stipulationD level of effort proposalE request for proposal

    答案解析
  • 78The process of choosing/documenting the best approa

    78 The process of choosing documenting the best approach to achieve the project objectives is part of: A The scope baseline B Scope authorizationC Scope definitionD Scope planning E All of the above

    答案解析
  • 13A legally binding document offered unilaterally is a _____ . A.purchase order Bscope of

    13 A legally binding document offered unilaterally is a _____ A purchase orderB scope of work descriptionC contract stipulationD level of effort proposalE request for proposal

    答案解析
  • 139The project charter is a document designed to tell _____ exactly what the project entai

    139 The project charter is a document designed to tell _____ exactly what the project entails A The project managerB The project officeC The project teamD The project sponsorE Anyone associated with the project

    答案解析
  • 95A legally binding document offered unilaterally is a _____ . A.purchase order B.scope of

    95 A legally binding document offered unilaterally is a _____ A purchase orderB scope of work descriptionC contract stipulationD level of effort proposalE request for proposal

    答案解析
  • ●The process of choosing/documenting the best approa

    ● The process of choosing documenting the best approach to achieve the project objectives is part of:A The scope baseline B Scope authorizationC Scope definitionD Scope planning E All of the above

    答案解析
  • ●The project charter is a document designed to tell

    ● The project charter is a document designed to tell _____ exactly what the project entails A The project managerB The project officeC The project teamD The project sponsorE Anyone associated with the project

    答案解析
  • 94The primary source document for establishing the content of the Project Status Report is

    94 The primary source document for establishing the content of the Project Status Report is:A The project charterB The Project PlanC The ASTM Project Document GuideD The summary work breakdown structure

    答案解析

最新问题

Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5