A negative cost variance and positive schedule variance means:
A The project is under budget and ahead of schedule
B The project is over budget and behind schedule
C The project is over budget and ahead of schedule
D The project will be overrun but ahead of schedule at completion
发布时间:2024-04-25正确答案:C
He was in a hurry and left things in a real ______.A.mixtureB.confusionC.messD.mass
He was in a hurry and left things in a real ______ A.mixtureB.confusionC.messD.mass
答案解析Mrs. White's husband tried to ______.A.cheer her
Mrs White "s husband tried to ______ A.cheer her upB.stop her from going to the supermarketC.stop her from buying unnecessary thingsD.make her less happy
答案解析--Could you do me a favor and take the box up to the sixth floor?--_______. A.
--Could you do me a favor and take the box up to the sixth floor?--_______ A. With pleasureB. My pleasureC. No wonderD. No comment
答案解析Advertisers tend to think big and perhaps this is why they're always coming in fo
Advertisers tend to think big and perhaps this is why they "re always coming in for criticism _____________________________________________________________________________
答案解析The boyA. wore new and nice clothesB. had much money in his handC. was from a poo
The boyA. wore new and nice clothesB. had much money in his handC. was from a poor familyD. wanted to get a doll very much
答案解析You have been assigned as a project leader and must first review the statement of work pro
You have been assigned as a project leader and must first review the statement of work provided by the customer Which of
答案解析Graphical displays of accumulated cost and labor hours plotted as a function of time are
Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:A Variance reportsB S curvesC Trend analysisD Earned value reportingE Baseline control
答案解析Researching organizing and recording pertinent information is called:A.Alternative analys
Researching, organizing and recording pertinent information is called:A Alternative analysisB Information gatheringC Configuration managementD Post project analysisE All of the above
答案解析QUESTThe scope baseline once established and approved is used:A.as the basis for making f
QUESTThe scope baseline once established and approved, is used:A as the basis for making future decisions B to accomplish verification measures C to evaluate potential changes D All of the above E A and C only
答案解析The identification definition and selection of the project objectives as well as the bes
The identification, definition, and selection of the project objectives as well as the best approach to achieving the project
答案解析Copyright © 2016-2023 114题库网(114158.com)All Rights Reserved.  免责声明 豫ICP备19007809号-5