A negative cost variance and positive schedule variance means:AThe project is under budget

A negative cost variance and positive schedule variance means:

A The project is under budget and ahead of schedule

B The project is over budget and behind schedule

C The project is over budget and ahead of schedule

D The project will be overrun but ahead of schedule at completion

发布时间:2024-04-25
参考答案

正确答案:C

相关问题
  • He was in a hurry and left things in a real ______.A.mixtureB.confusionC.messD.mass

    He was in a hurry and left things in a real ______ A.mixtureB.confusionC.messD.mass

    答案解析
  • Mrs. White's husband tried to ______.A.cheer her

    Mrs White "s husband tried to ______ A.cheer her upB.stop her from going to the supermarketC.stop her from buying unnecessary thingsD.make her less happy

    答案解析
  • --Could you do me a favor and take the box up to the sixth floor?--_______. A.

    --Could you do me a favor and take the box up to the sixth floor?--_______ A. With pleasureB. My pleasureC. No wonderD. No comment

    答案解析
  • Advertisers tend to think big and perhaps this is why they're always coming in fo

    Advertisers tend to think big and perhaps this is why they "re always coming in for criticism _____________________________________________________________________________

    答案解析
  • The boyA. wore new and nice clothesB. had much money in his handC. was from a poo

    The boyA. wore new and nice clothesB. had much money in his handC. was from a poor familyD. wanted to get a doll very much

    答案解析
  • You have been assigned as a project leader and must first review the statement of work pro

    You have been assigned as a project leader and must first review the statement of work provided by the customer Which of

    答案解析
  • Graphical displays of accumulated cost and labor hours plotted as a function of time are

    Graphical displays of accumulated cost and labor hours, plotted as a function of time, are called:A Variance reportsB S curvesC Trend analysisD Earned value reportingE Baseline control

    答案解析
  • Researching organizing and recording pertinent information is called:A.Alternative analys

    Researching, organizing and recording pertinent information is called:A Alternative analysisB Information gatheringC Configuration managementD Post project analysisE All of the above

    答案解析
  • QUESTThe scope baseline once established and approved is used:A.as the basis for making f

    QUESTThe scope baseline once established and approved, is used:A as the basis for making future decisions B to accomplish verification measures C to evaluate potential changes D All of the above E A and C only

    答案解析
  • The identification definition and selection of the project objectives as well as the bes

    The identification, definition, and selection of the project objectives as well as the best approach to achieving the project