The extent of project management techniques to be used on a project are determined mainly by the _____ and _____ of the project.
A . budget, schedule
B . quality requirements, schedule
C . size, type of industry
D . nature, size
E . project manager, sponsor
发布时间:2024-04-25正确答案:D
The time necessary to complete a project is called the _______ of a project.A.Implementati
The time necessary to complete a project is called the _______ of a project A Implementation TimeB Life CycleC Operation TimeD Critical PathE Completion Phase
答案解析You have been assigned as a project leader and must first review the statement of work pro
You have been assigned as a project leader and must first review the statement of work provided by the customer Which of
答案解析During the planning phase of a project you realize that more than one functional departme
During the planning phase of a project, you realize that more than one functional department possesses the skill and technic
答案解析The most common definition of project success is:A.Within timeB.Within time and costC.With
The most common definition of project success is:A Within timeB Within time and costC Within time, cost and technical performan
答案解析The appointment or selection of a project sponsor is often based upon:AThe strategic impor
The appointment or selection of a project sponsor is often based upon:AThe strategic importance of the projectBWho the custom
答案解析Interfacing with the customer after project go-ahead
Interfacing with the customer after project go-ahead is the responsibility of:AProject sponsorBProject teamCProject managerDFuncti
答案解析The scope baseline/project charter is prepared by th
The scope baseline project charter is prepared by the:AProject managerBProject manager and project officeCProject manager, projec
答案解析In preparing a good project definition experienced project managers will:AConcentrate mai
In preparing a good project definition, experienced project managers will:AConcentrate mainly on the end product rather than c
答案解析Selection criteria for project selection include:A.cost versus benefitB.riskC.contribution
Selection criteria for project selection include:A cost versus benefitB riskC contribution towards organizational goalsD rate of returnE All of the above
答案解析The use of the project reports:A.are not necessary on small projectsB.provides a means whe
The use of the project reports:A are not necessary on small projectsB provides a means whereby various levels of authority ca